From the first pre-consultation to the day you may open is three to six months, and about four and a half to eight months if you count through to the first booking.
The calendar is not spent on paperwork. It goes on construction, on inspections, and on the six weeks between listing the property and a booking arriving. This is the record of a company that took three buildings and six rooms through the hotel-business permit (旅館業許可) in Tokyo and Sapporo and still runs them itself. Figures are as of 1 October 2026, from our own six rooms over the twelve months from October 2025 to September 2026, with the method published on our operating data page. The permit procedure itself is in getting a hotel-business permit, and the sequence of the steps, sorted by how cheaply you can still walk away, in starting a rental in Japan. This article is about how long that sequence takes.
How long does it take from the first enquiry to opening?
Three to six months until the permit is issued, plus the six weeks between listing and the first booking: about four and a half to eight months counted from the first pre-consultation. Three months plus six weeks is four and a half; six months plus six weeks is seven and a half, carried to eight for slack.
If the total floor area is over 200 square metres, a change-of-use building confirmation (建築確認申請) is required and the schedule stretches further, as it does when the fire-equipment work is large. Hurrying does not shorten the individual stages. What decides each one is whose clock it runs on.
| Stage | Whose clock it runs on | How long |
|---|---|---|
| Checking the address and the building | Yours | Thirty minutes |
| Choosing the permit or the notification route | Yours | Half a day |
| Pre-consultation: health centre and fire department | The counter's diary | As offered |
| Drawings, building work, fire equipment | Designer and contractor | Most of the total |
| Briefing the neighbours | The neighbours | Cannot be done twice |
| Fire inspection, application, site inspection | Fire department and health centre | The inspection date |
| Furniture, equipment, photography | Yours | After the work |
| Listing to first booking | Guests | 42 days median |
Which part of the wait can an owner actually shorten?
Only the stages whose clock is yours. Compress the address check, the choice of framework, the furniture delivery and the photography all at once and you have saved a few weeks.
Everything else sits on a counter's appointment diary, a contractor's schedule, an inspection date, and on when guests happen to book. So the schedule is not won by moving faster. It is won by running things in parallel and by not creating a re-do. The things that can run alongside the building work are the groundwork for the neighbour briefing, choosing furniture and supplies without ordering them, planning the listing copy and the photographs, and deciding whose name the listing account and the contract go in. That last one sets what leaving costs later, so it is settled before opening (reading a management contract).
What stretches the schedule most?
Not new work: re-done work. What eats the months before a permit is the construction and the inspections rather than the documents, so when an assumption behind the work changes late, the whole of that change lands on the calendar.
Four places produce most of the re-dos. How far each one sets you back varies by property, so rather than trying to predict the delay it is safer to plan so that none of the four happens. What each one involves is set out in getting a hotel-business permit.
- No existing drawings: common in older houses. The work starts with redrawing them, which raises both the time and the cost a step
- Fire consulted after the interior is decided: the equipment requirements arrive and the interior has to be decided again. The consultation belongs before the interior
- Taking the neighbour briefing lightly: an objection takes longer to settle than the permit itself
- Leaving the water-quality test late: in a building with a storage tank it stops you just short of the application

If you can choose the opening month, which month should it be?
If you can choose, do not open into that city's weakest month. The opening month is the hardest month you will ever sell, because the listing has no reviews yet, and a market trough on top of that thins the first month twice over.
Where the trough sits differs by city. Across our own six rooms over twelve months, Tokyo's lowest month and Sapporo's lowest month are ten months apart.
| Rooms | Lowest month | Highest month |
|---|---|---|
| Tokyo, three rooms | September 2026, 60.0% | October 2025, 95.2% |
| Sapporo, three rooms | November 2025, 68.3% | February 2026, 94.0% |
| All six rooms | September 2026, 71.7% | October 2025, 90.3% |
Measured 1 October 2026 across our own six rooms. This is our record, not a figure promised to anybody else's property. How the two cities move against each other is in seasonality. Since the listing has to be live six weeks before the month you want to earn in, the month to walk into the pre-consultation is that month minus four and a half to eight.
What can you do during the months of waiting that costs nothing?
Three things move forward without money: preparing the neighbour briefing, planning the listing copy and the photographs, and sorting out the names on the account and the contract. None of them depends on how the building work is going.
Furniture and equipment are chosen but not ordered. Bought before the permit looks likely, they wait months in a room you cannot use or in storage. Photography comes after the furniture, so all the waiting time buys is deciding how many pictures to take and in what order. Only a handful of a listing's photographs are guaranteed to be seen in a search, and how we choose those is in photographs and listing copy.

How long after listing does the first booking arrive?
A median of 42 days, which is six weeks exactly. Across 489 of our own reservations the median gap between booking and arrival was 42 days (measured 1 October 2026, our six rooms over twelve months).
So what sells in the days after a listing goes live is mostly dates more than six weeks out; the near-in nights fill later. On top of that, the opening month has no reviews, and at the same price a room with a record is chosen first. Price confidently in that month and the first booking moves further away. Our six rooms carry 398 reviews averaging 4.9, but that took more than twelve months to accumulate. How to use lead time is in booking lead time, and how a rating is built in guest ratings.
What begins on the day you are allowed to open?
Nothing ends on the day the permit is issued. What begins is the work that repeats every month and every year, and the operational load is at full rate from the first month.
Our average stay is 3.3 nights, and 489 reservations divided by six rooms and twelve months is about 6.8 arriving parties a room-month. Cleaning runs 17.0% of revenue and seven operating cost lines together 27.8% (rent and management fee excluded, water absent from the source workbook). Fire equipment goes onto a calendar of twice a year and once a year, and the accommodation tax (宿泊税) becomes a monthly routine. The inspections are in fire inspections after opening and the tax in who pays the accommodation tax.
Where in this calendar should an owner talk to a management company?
Before the building work is ordered. Most of the schedule is decided by what the construction and the fire equipment contain, and that can only be changed before the order goes out.
Owners often reach us after the permit is in hand, and by then the parts that drive the calendar are set in the building. We take properties only in the 23 wards of Tokyo and in Sapporo, at most five at a time, and we do turn properties down at the inspection (the properties we turn down). The fee is performance-based from 20% of revenue, with nothing fixed to pay in a month without bookings. AG STAY holds no 住宅宿泊管理業者 registration, so we do not take on a property that stays under the notification route.
Talk through the calendar for your property